Midway Renovation Final Chapter - June 17, 2018

On June 8th the cement wall was removed from the Midway main entry so that the final chapter of this project - the remodel of the front office and library - can begin. With the front office "gone" the Midway office has temporarily moved to the old Northwood building where they are open for business June 15-27 from 8 am to 3 pm. The renovation of these two spaces will be completed by August 21 when the office will reopen following summer break.
Read More »

Shiloh Hills Renovation - June 16, 2018

Lots of demolition taking place at Shiloh Hills. Pictures show the back wall removed in preparation for expanding the school's north facing footprint to include a new lunch/multi-purpose room adjacent to the new school kitchen.
Read More »